Arbitration clause - Contract concluded under the PLAN Cluster D programme - Travel expenses - Costs of recovery - Late payment.

ECLI: ECLI:EU:T:2004:181Decision of: 10.06.2004

Case T-315/02 Svend Klitgaard v Commission of the European Communities (Arbitration clause – Contract concluded under the PLAN Cluster D programme – Travel expenses – Costs of recovery – Late payment) Judgment of the Court of First Instance (Fifth Chamber), 10 June 2004 ?II-0000 Summary of the Judgment Procedure – Referral to the Court of First Instance under an arbitration clause – Contract providing for Community financial assistance for arranging a technical audit – Application for reimbursement of travel costs and for payment of recovery costs – Dismissed (Art. 238 EC) JUDGMENT OF THE COURT OF FIRST INSTANCE (Fifth Chamber)10 June 2004(1) (Arbitration clause – Contract concluded under the PLAN Cluster D programme – Travel expenses – Costs of recovery – Late payment) applicant, v defendant, THE COURT OF FIRST INSTANCEOF THE EUROPEAN COMMUNITIES (Fifth Chamber), gives the following On those grounds, THE COURT OF FIRST INSTANCE (Fifth Chamber) Lindh García-Valdecasas Cooke H. Jung P. Lindh Registrar President 1 – Language of the case: Danish.

© Europäische Union, EUR-Lex · CELEX 62002TJ0315

Official language versions

This decision is available in the following official languages of the Union — all equally authentic.

ČeštinaΕλληνικάEnglishEspañolFrançaisItalianoNederlandsPolskiPortuguês